Μεταξύ των αξόνων 8 ως 10 έχουν σημειωθεί 3 κατεβάσματα χυτοσιδηρών σωλήνων διαμέτρου 125. Στην κάτοψη του επιπέδου -1 δεν έχουν σημειωθεί στα αντίστοιχα σημεία κατεβάσματα σωλήνων. Παρακαλώ διευκρινήστε.
Between the axles 8 through 10 are noted three downshifts cast iron pipe diameter 125. In the plan view of level -1 are not noted at the points downshifts tubes. Please please specify.
Between the axes 8 to 10 there have been 3 drops of cast iron pipe 125 diameter. The floor plan of level-1 has not been noted in the corresponding points of pipe downloads. Please specify.
Three downloads of 125-diameter cast-iron tubes have been recorded between axes 8 to 10. At the level-1 slope, there were no tube downloads at the respective points. Please clarify.<br>