is a performance measurement indicator which indicates in percentage the divergence that has work in relation to the current schedule. specifically, calculated as follows: Schedule Slippage = (actual duration of project-planned duration of the project/project period) * 100The formula for calculating the actual duration of the project is as follows:Actual project duration = actual project end date-actual project start dateThe formula for calculating the planned duration of the project or planned duration:Planned project duration = Scheduled expiration date-scheduled start date